• 6.000 t/day
• Outer Diameter: 18.800mm
• Inner Diameter : 18.000mm
• Height: 63.300mm
• Tensioning H...
TheartofEngineering
SYSTEM ANALYSIS TABLE
No Descriptions Qty / Pcs. Dimensions
1. 12C15 Layout 15 Layout 2x9.260x15x3,14x...
TheartofEngineering
Hydraulic Jack Type
• ZPE-12St2
• Piston Area: 309 cm2
• 210Kg
Hydraulic Pump Type
• Wheel-Mounted Str...
TheartofEngineering
1.Day
2.Day
3.Day
4.Day
5.Day
6.Day
7.Day
8.Day
9.Day
10.Day
11.Day
12.Day
13.Day
14.Day
15.Day
16.Day...
TheartofEngineering
Prestressing Service with Hydraulic Tensioning Methode
• 1&2 Pcs. Hydraulic Pump Station
• 2&4 Pcs. Hy...
TheartofEngineering
Other Details
• Wide Scaffolding for Working Area
• Material Elevator for Lifting the Hydraulic Equipm...
TheartofEngineering
No Description Specs1 Specs2 Qty Unit Unit Price Total Price
1. Hydroulic Station Usage Fee 1860 N/mm2...
TheartofEngineering
w w w . B e r r C o n s u l t i n g . c o m
+90 532 163 62 90
+90 216 395 20 34
Info@BerrIndustry.com
...
of 11

Prestresed Concrete Tank Proposal and Study

Prestresed Concrete Tank Proposal and Study. Post-Tensioning, Pre-Stressing, Hydraulic Equipment Supply
Published on: Mar 4, 2016
Published in: Engineering      
Source: www.slideshare.net


Transcripts - Prestresed Concrete Tank Proposal and Study

  • 1. TheartofEngineering www.BerrIndustry.com www.BerrMuhendislik.com
  • 2. TheartofEngineering
  • 3. TheartofEngineering
  • 4. TheartofEngineering • 6.000 t/day • Outer Diameter: 18.800mm • Inner Diameter : 18.000mm • Height: 63.300mm • Tensioning Height: 50.307mm • Concrete: C30 • Steel : S420 Specifications
  • 5. TheartofEngineering SYSTEM ANALYSIS TABLE No Descriptions Qty / Pcs. Dimensions 1. 12C15 Layout 15 Layout 2x9.260x15x3,14x1,185=1.034.277mm 2. 9C15 Layout 8 Layout 2x9.260x15x3,14x1,185=1.034.277mm 3. Amount of the 12C15 Tendons ( Cables ) 4x15 = 60 pcs. Cable A1-A2-A3-A4 4. Amount of the 9C15 Tendons ( Cables ) 4x8 = 32 pcs. Cable B1-B2-B3-B4 5. Amount of the NC15 TrumPlates 4x2x15 = 120 pcs. 225 to 80 x570 mm Internal 6. Amount of the NC15 TrumPlates 4x2x8 = 184 pcs. 195 to 72 x513 mm 7. Amount of the Spiral 4x2x23 = 184 pcs. 310 x 350 8. Amount of the C15 Wedge 4x2x23 = 184 pcs. 160 x 45 mm 9. Post Tension Cable Sleeve For 12C Ø80 10. Post Tension Cable Sleeve For 9C Ø72 11. Anchor Grouting 4x2x23 = 184 pcs.
  • 6. TheartofEngineering Hydraulic Jack Type • ZPE-12St2 • Piston Area: 309 cm2 • 210Kg Hydraulic Pump Type • Wheel-Mounted Strand Pushing • 1860 N/mm2 – 335 bar – 25 ton • 160 Kg Internal TrumPlate
  • 7. TheartofEngineering 1.Day 2.Day 3.Day 4.Day 5.Day 6.Day 7.Day 8.Day 9.Day 10.Day 11.Day 12.Day 13.Day 14.Day 15.Day 16.Day 17.Day 18.Day 19.Day 20.Day 21.Day 22.Day 23.Day 24.Day 25.Day 26.Day 27.Day 28.Day 29.Day 30.Day 31.Day 32.Day 33.Day 34.Day 35.Day 36.Day 37.Day 38.Day 39.Day 40.Day 41.Day 42.Day 43.Day 44.Day 45.Day 46.Day 47.Day 48.Day 49.Day 50.Day 51.Day 52.Day 53.Day 54.Day 55.Day 56.Day A A.1 SITE INSPECTION A.2 EQUIPMENT CONTROL A.3 METHODE OF STATEMENT LIST A.4 MATERIAL CHECK LIST B B.1 1th SILO 12C15 B.2 1th SILO 9C16 B.3 2nd SILO 12C15 B.4 2nd SILO 9C15 B.5 1th SILO Tension Control & Test by Client B.6 2nd SILO Tension Control & Test by Client NOTE-1 NOTE-2 NOTE-3 NOTE-4 NOTE-5 NOTES Scaffolding has to be done before start to prestressed operation. Equipment Elevator has to done before works. Components must be located in the field. ( cables, trumplates, spirals, wedges,… ) Necessary Equipment must be located in the field. Site Survey Report must be prepared before agreement by the client's supervisor. Schedule 20.05.2015PRESTRESSED CONCRETE SITE PREPARING OPERATION
  • 8. TheartofEngineering Prestressing Service with Hydraulic Tensioning Methode • 1&2 Pcs. Hydraulic Pump Station • 2&4 Pcs. Hydraulic Jack • 2&4 Pcs. Hydraulic Toolbox • 2 Galon Hydraulic Oil Barrel • 2 Pcs. Table Lifter • 2 Pcs. Electrical Connector • 1 Supervisor, 2 Foreman, 4 Mechanical Workers, 2 Helper • PreTensioning Works and Reporting
  • 9. TheartofEngineering Other Details • Wide Scaffolding for Working Area • Material Elevator for Lifting the Hydraulic Equipment • Cable ( Steel Rope Tendons ) • Steel Pipe Cover • Duct, Trumplate • Wedges, Spirals • Other Consumables • Grounding Works • Testing and Measurement Works • General Costs ( Accommadation, Food, Fuel, Water, Security, Flight Tickets, etc... ) • 4 Local Helper, 1 Superintendent ( Auditor )
  • 10. TheartofEngineering No Description Specs1 Specs2 Qty Unit Unit Price Total Price 1. Hydroulic Station Usage Fee 1860 N/mm2 335 bar / 25 ton 2 Pcs. 2. Fieldwork Price 7 Workers 1 Foreman / 1Supervisor 2 Prs Payment Methode: This price is valid for a 60-day working with 9 personel in the field ( according to the related time schedule ). ▪ Cash Advance : %50 ▪ Progress Payment : %25 ▪ Completion Payment : %25 Additional : ▪ Extra Equipment Box Rent Cost: 1.100,-USD per day ▪ Extra Supervising Service Cost : 2.100,-USD per day ▪ Equipment Box Sales Price : 190.000,-USD The Cost is 100$ per day for In temporary standby time. ( Max. 30 Days...) 2 x ( Hydraulic Pump, Tensioner, Ejector, Table Lift ) This price has been prepared for the works of two ( double ) silos.
  • 11. TheartofEngineering w w w . B e r r C o n s u l t i n g . c o m +90 532 163 62 90 +90 216 395 20 34 Info@BerrIndustry.com www.BerrIndustry.com www.BerrMuhendislik.com

Related Documents