Assets and Technical Services- Fortnightly Update
Update 6
~ Murray Valley Number 1 - Decommissioning works complete
7 Jun...
of 1

Poole, Mark-Article GMW ATS Newlsetter-2007-p1

Published on: Mar 4, 2016
Source: www.slideshare.net


Transcripts - Poole, Mark-Article GMW ATS Newlsetter-2007-p1

  • 1. Assets and Technical Services- Fortnightly Update Update 6 ~ Murray Valley Number 1 - Decommissioning works complete 7 June 2007 Docs# 2173639v7 G-MW, in partnership with the Moira Shire Council, have recently constructed a new pump station and pipeline from the Murray River downstream of Cobram, which has allowed the decommissioning of the Number 1 channel through Cobram township. The new pump station has been successfully operating this season and has supplied almost 6,000 ML to the customers on the Number 1 channel downstream of Cobram. The pump station has been designed to operate under River Murray floods, but due to extremely tight timelines and predicted low river levels, flood commissioning was deferred. This commissioning has now been successfully completed. Some subsidence occurred during this commissioning, and the Contractor will return to rectify shortly. The major task associated with the decommissioning was the Town Siphon. The siphon is a 375m long cast insitu 1200mm nominal diameter concrete pipe that runs under three roads (including the main road to Barooga), St Joseph's Primary School, 4 house lots and the Cobram hospital, surfacing in the middle of the hospital carpark. Over 470 cubic metres of low strength grout was used to fill the pipeline. This task was managed by Mark Poole (ATS- Technical Services) with support from Dave Darby (Murray Valley) and a number of Murray Valley Staff who undertook the supervision of concrete trucks, traffic management and excavation and refill of the inspection/fill points along the pipeline. The final structure abandonment on Campbell Rd (see photo) was completed at the end of April 2007. The end structures were removed, two water supply pipelines were relocated and pipes filled with grout. Three other road culverts have been abandoned·and 3km of channel has been pushed in and graded. New Pump station Campbell Rd post abandonment of G-MW culvert Contact: Peter Egglestone ~ Shepparton Modernisation Project Under G-MW's Wateright2020 quest to save 400,000ML the $188M Shepparton Modernisation project was born. The Shepparton Modernisation project involves a number of water saving measures including channel automation, pressure pipelines, gravity pipelines, improved metering and targeted maintenance. The project business case is being prepared by P&E (Water Savings Unit) and is currently being finalised with DSE while implementation of the works will be managed by ATS (Major Projects Unit). In May 2007 the Minister for Water announced $37.5M to commence the project in 2007 while the finer details of the business case are being negotiated between G-MW/DSE. Works are scheduled to commence late into the 2007 winter maintenance period and involve automating channel control structures along the East Goulburn Main (EGM). Extensive planning has been undertaken by Major Projects, in partnership with the Shepparton Area, Technical Services, the Reconfiguration Planning team and principal contractor Rubicon, to ensure that G-MW could deliver on the Government's May commitment that works would commence in 2007.

Related Documents