Nakibul HAQUE
Project Planning & Controls - ECP
ProfessionalExperience Summary
Inserta
photo
here if
necessa
...
Page 2 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
Project Control
System Establish and implementthe project con...
Page 3 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
Detailed ProfessionalExperience
Senior Planning Engineer (Jul...
Page 4 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
Project Title:NEB Phase III Development FEED Services (Al Dab...
Page 5 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
Participates in the negotiations on projectcontrol aspects wi...
Page 6 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
From Mar-2014 to Apr-2014
Project Title- BASRAH GAS COMPANY A...
Page 7 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
provide operational flexibilityand improvementin availability...
Page 8 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
Project Title : KGOC Gas and Condensate Export System (KGACES...
Page 9 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
Project Title : AL DABB’IYA ASR GAS DEVELOPMENT
PROJECT- FEED...
Page 10 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
 Definesthe Projectbreakdownstructures.
 Plansso as to ens...
Page 11 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
Prepare initial network of activities in simplified form for...
Page 12 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
 Preparation of monthlyfinancial reports for the project. A...
Page 13 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
Ensure reconciliation on a quarterly basis between Field Cos...
Page 14 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
102010-00205ConsultancyService for Gas Leak and Fire Study o...
Page 15 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
Responsible for coordinating Engineering,procurementand Cons...
Page 16 of 16
Nakibul HAQUE
Project Planning & Controls - ECP
Responsibilities: Documentation and computer back-up data co...
of 16

Nakibul Haque_CV FEB16

Published on: Mar 3, 2016
Source: www.slideshare.net


Transcripts - Nakibul Haque_CV FEB16

  • 1. Page 1 of 16 Nakibul HAQUE Project Planning & Controls - ECP ProfessionalExperience Summary Inserta photo here if necessa ry CAREER OBJECTIVE: Consistently achieve comprehensive growth professionallyby diligently applying my skills to plan, manage and control successfully the multi EPC projects as per scope, optimizing resources, within the costbudgetfor on-time completion with teamwork achieving the highest benchmark of quality and safety. 12+ Years of Overseas experience in the field of Project management, Planning & Control function (Office & Site Construction planning), which includes multi-disciplinary activity of providing Conceptual , FEED, EPC, EPCM & EPIC services for various projects in Refineries, Power plants, Petrochemicals, LNG Pipeline & Power Plant , Onshore and Off-shore Oil & Gas Pipeline & Facilities.  12 years plus, Out of which: More than 2 Years in Technip-France-Abu Dhabi Less than 4 Years in Worley Parsons-Singapore Less than 1 year in Foster Wheeler Asia Pacific-Singapore More than 1 Years in Olayan Descon Engineering LTD-KSA More than 2 Years in Descon Engineering LLC-Qatar Less Than 1 year in SBGGroup-Saudi Arabia  Major Experiences; Offshore/Onshore Oil & Gas Pipeline & Facilities Gas producer wells,Flow Line from Well-head to Gas Treatment Unit (GTU), Trunk line from GTU to Central Process facilities (CPF), SRU & Utilities/ off sites. Wellhead platform & associated W/H facilities,Water injection platform & Gas Injection platform. Onshore Power Plant / Refineries, Pipe Line Projects. Petrochemical Complexes– Poly Propylene unit (PP), HDPE, LLDPE, associated off-sites & utilities. LNG Pipelines & Power Plant – Expansion/ Modification and shutdown.  Computer Education MS Office (Word, Excel & Power Point) & Oracle E-Business. Project Planning Software (Primavera, MS Project) Project Control System (PROCESS by Descon Engineering, INCONTROL (WP- SINGAPORE) & JANUS (TP-France). Education  Degree (BE) in Mechanical Engineering, AMU India 1999. Training  In-house Worley Parsons PCDP.  Oracle P6 Training by WP-Malaysia team  Quality, Safety and Code of Conduct Training by SBG, OLAYAN, DESCON, FW, WP & TECHNIP. Language  English-Fluent  Urdu/Hindi-Fluent  Arabic-Read only. Contact  +91-9792185139  +971-563662650  nakib2003@gmail.com  nakib2003@yahoo.com  nhaque@technip.com Inserta photo here if necessa ry
  • 2. Page 2 of 16 Nakibul HAQUE Project Planning & Controls - ECP Project Control System Establish and implementthe project controls process and system,Procedures for planning, progress monitoring,and Trending and projectexecution plan. Provide leadership to the Project Controls team to develop, implement& maintain the projectcontrols procedure, schedules and reporting systems. WBS Develop Work Break down Structure (WBS) by decomposing top to bottom from phase,disciplines,plant,area, subsystems and work packages. Schedules Management Define activities for each work package,Sequence activities,compute and allocate resources as standard man - hours applying productivities to Lev.4 Quantities. Prepare weekly progress & Qty ‘S’ curves, manpower histograms. Prepare,administer & control baseline Level 3 integrated EPC schedule Detailed scheduling and monitoring ofcritical activities with zero total float Direct Subcontractors for preparation of Level 4 schedules,link and back integrate into Level 3 schedule aggregating bottom to top approach. Control Three weeks look ahead schedule,contractkey dates and milestones Cost Management Develop cost managementprocedure & CostBreak down Structure (CBS). Invoicing to clientbased on achieved monthlyprogress %. Aggregation of Subcontractor’s paymentas per unit rates. Compute forecastcostbased on the revised budget, estimate to complete and committed costto detect any deviation (overrun/under run). Update contingencyreserves reductions.Ensure Costreportvariations are analysed and highlighted. Change Management Develop Change managementprocedure.Perform integrated change Control. Review scope change requests and variations for cost& schedule impact Claim managementand Delayanalysis Material Management Ensure timelyrelease ofDeliverables (drawings & materials).To compute feasibilityand construction work front based on deliverables and accessibility.Implementconstructabilityfor VEP (Value Enhancing Practice) To perform the piping feasibilityexercise for prefabrication and erection in Marian software after linking IFC isometrics and piping bulk material. Contracts Management Responsible ofmanaging OutSourcing of services thatincludes preparation ofTender documents, cost comparison & evaluation coordination etc. Reporting Responsible for schedule and costreviews,monthly/weekly reports,progress reporting,Higher Management Reporting (Dailyprogress trend,Weekly Criticality, Synthesis Monthly Reporting).Maintain commoditydatabase. Streamline in and out information flow for performing ProjectControls functions with authentication,Training, Mentoring and Team Building.
  • 3. Page 3 of 16 Nakibul HAQUE Project Planning & Controls - ECP Detailed ProfessionalExperience Senior Planning Engineer (Jul 2013 – till date) 2013-Present Technip, Abu Dhabi From Jul-2013 to Aug-2013 Project Title- Umm Lulu Project (EPC1) Client- ADMA OPCO Abu Dhabi Responsibilities: 1-Prepared Micro-Schedule up to Purchase ORDER for Critical equipmentfor close monitoring. 2-Monitoring and coordinating with Lead Engineers for progress and better performance. From Jul-2013 to Feb-2014 Project Title: RUMAITHA &SHANAYEL PHASE III DEVELOPMENT (FEED) Project to handle an additional production of 39 MBOPD from Rumaitha and Shanayel fields by 2016. The Contract is split in 2 Packages:  Package-01 (firm scope): FEED for Rumaitha / Shanayel Phase III Development considering the scenario of Hydrocarbon (HC) Water Alternating Gas (WAG) for the Enhanced Oil Recovery (EOR)  Package-03 (firm scope): - Feed for RumaithaNorth CO2 Injection Project, for conversion of Ra Ph1 Zone B developmentfrom currentHC WAGscheme to CO2 Injection. Client- ADCO Onshore Company Abu Dhabi Responsibilities : Project close out Report. Finalization of spent man-hours. Submission of VO weekly and other reports.
  • 4. Page 4 of 16 Nakibul HAQUE Project Planning & Controls - ECP Project Title:NEB Phase III Development FEED Services (Al Dabbiya) Phase III of the Al Dabb’iya field developmentis planned to deliver an additional 73 MBOPD by 2017. Al Dabb’iya Phase III will be developed through new facilities and in proximity to the existing Dabb’iya plant. The new facilities include:  New clusters/gathering stations for production and injection.  Additional oil and gas processing trains adjacent to existing CPP facilities  Additional Oil export facilities.  New gas export facilities Client- ADCO Onshore Company Abu Dhabi. Responsibilities: As Senior Planning Engineer is in charge of rendering Planning,Scheduling and Monitoring services effectively and as per Technip Planning Procedures and contract requirements ,responsible for highlighting areas ofconcerns and solutions to help achieve a successful and timelycompletion ofProjects & follows up closely with vendors and subcontractors on the execution of projectProcurementand Manufacturing schedules,maintaining close liaisons with Technip Procurement Division and Inspection Unitat all times for proper follow-up. For assigned projects,is in charge of setting up:  Project Calendar  Planning Procedures  Progress Measurementprocedures  Reporting procedures  Work Breakdown Structure (WBS)  OBS Also in charge of creating the 2 key schedules per projectphase:  ProcurementSchedule:from Material Requisition till Purchase Order Placement  Manufacturing Schedule:from Purchase Order Placementtill Material receipt Discusses the outcome ofthe above planning in terms ofschedules and procedures with the PM and / or Lead Discipline Engineers in order to achieve a final project plan. Regularlyreviews the manpower plan to check compliance with ContractTerms & Conditions; Incorporates team comments and issues final schedule to Clientfor approval; Holds discussions with Clientrepresentatives over the schedule and incorporates comments into the schedule;Issues the final Implementation Plan.
  • 5. Page 5 of 16 Nakibul HAQUE Project Planning & Controls - ECP Participates in the negotiations on projectcontrol aspects with Vendors and Contractors;Reviews and commenton Contractors'and Vendors'schedules; Issues revised schedules including corrective actions. Prepares progress measurementprocedures for all phases ofthe project including determination ofweightfactors. Collects and compiles back-up data for project statistics and ratio calculations. Undertakes projectfollow-up ofprogress monitoring,working to update the project schedule with actual inputand activity progress;Issues the updated schedule status along with the trend analysis schedule showing forecastdates for group information purposes. Provides assistance to the Project Manager on projectdelays,reasons and corrective action suggestions. Sets up and issues the DocumentRegister;Prepares Level 3 Listand Document Register using JANUS or MS Access. Prepares Planning attachments for Weekly Progress Reports;Issues feedback to Project Managers for onward transmission to client; Prepares and issues Planning attachments for Monthly Progress Reports.These include:  Updated Projectschedule  Updated Documentregister  Progress Statistics  Progress S - curves covering all phases ofthe project  Manpower Histograms  Milestones Status Report  Exceptional reports such as “Activity behind Schedule"or the "Activity Due Plan" for the following week or month. Prepares a detailed network using projectmanagementsoftware (such as MS Project or Primavera) ; Ensures the update and maintenance ofPlanning software applications. Reviews and comments on vendor schedules,as well as progress reports for various purchase orders;Monitors timelyexecution of such orders closely;Informs the Project Manager in case of delay and suggests corrective actions. When assigned a Lead Planning Engineer position,takes charge ofpreparing the Engineering DocumentRegister and the ProcurementDocumentRegister inclusive of all basic overall schedules (Levels 0,1 and 2) as well as Detailed Schedules (Level 3). Reviews Construction contractors'schedules and Progress Reports,provides comments and suggests corrective action. Contributes towards implementing both companyand clientHSE Management System objectives and procedures. Complies with corporate Quality standards as stipulated in the Quality Manual and its ensuing Procedures. Complies with the applicable companyprocedures for this Division as they are documented in the relevant DWP documentation.
  • 6. Page 6 of 16 Nakibul HAQUE Project Planning & Controls - ECP From Mar-2014 to Apr-2014 Project Title- BASRAH GAS COMPANY AR RATWAI NGL TRAIN 1 (FEED Project). New Greenfield associated gas processing facilities that will minimize flaring in Iraq – an NGL train with nominal feed gas capacity of 530 MMSCFD. OUTLINE OF PROJECT SCOPE : The PROJECT will comprise the following units/systems:  Inlet Receiving Booster Compression and Dew Pointing;  Condensate Stripping;  Acid Gas Removal (AGRU);  Sulphur Recovery (SRU);  Dehydration and Mercury Removal (DMR);  NGL Extraction;  Storage of chemicals, water and Propane refrigerant storage.  Utilities – Hot oil, propane refrigeration, high and low pressure fuel gas, flare, power generation, etc.  Administration and Plant Buildings Client- Basra Gas Company Khor Al Zubair, Basra (SHELL IRAQ). Responsibilities:  Prepared Planning Package  Co-ordination and follow-up for progress with engineering discipline.  Prepared Weekly/ Monthly Progress Report. From May-2014 to Till Date Project Title : AGFA-ADDITIONAL GAS SUPPLY TO ONSHORE AND FLEXIBILTY ASSURANCE (EPC PROJECT) Increase the total off take level of US KHUFF from 600 to 1600 MMSCFD by Third Quarter 2016 and up to 2025, and debottleneck certain facilities in USSC to
  • 7. Page 7 of 16 Nakibul HAQUE Project Planning & Controls - ECP provide operational flexibilityand improvementin availabilityof HP gas supply due to additional load from IGD Project. OUTLINE OF PROJECT SCOPE :  Installation of new TA Extension Platform to accommodate cooling and associated facilities for +200 Additional Gas scope. New 4 leg jacket with 3600 tonne integrated deck.  Topsides piping replacement at WHT’s US 216 and US 218 to produce gas from additional 3 wells and electrification of the two WHT’s  Installation subsea cable to US 216 and US 218 and electrification of the two WHT’s  Additional stabilization of existing pipelines to allow higher gas temperatures  Tie-ins at NGTP and new containerized substation on existing TA Platform  Installation of new Table Top structure on ABK TIP to accommodate cooling and associated facilities for gas from US-58 (hot gas limits production), including containerized substation, for AGFA flexibility gas supply and tie-ins at GTP.  Topsides piping replacement at WHT US 58 bridge linked to GTP to accommodate higher gas flow rates for additional flexibility supply. Client- ADMA OPCO Abu Dhabi Responsibilities :  Develop planning procedures,WBS and projectcalendar as per contract requirement.  Preparation of Starter Schedule / 90 Days Look Ahead Schedule for implementation until Planning Package was approved.  Preparation of Planning Package, which included Overall Level III Project Schedule, Progress Measurement System at Level IV, baseline progress curves and various histograms.  Progress and productivity monitoring.  Progress reporting to client and internal management.  Develop schedule trend analysis and propose corrective actions for slippages.  Develop Level 3 & Level 4 construction schedule including setting up construction progress measurement system.  Managed the Construction Planning Team and the Sub-Contractor Planning Team  Review, analyse and approve sub-contractor and vendor planning inputs and deliverables.  Support in establishing Cost Control procedures & Invoicing Mechanism.  Support Variation Orders.  Review and approve sub-contractor’s invoices and variation orders.  Issue various look-ahead plans and coordinate for inputs to achieve the targets.  Working in close co-ordination with ProjectManagementTeam for engineering deliverables expediting.
  • 8. Page 8 of 16 Nakibul HAQUE Project Planning & Controls - ECP Project Title : KGOC Gas and Condensate Export System (KGACES) (EPC PROJECT) OUTLINE OF PROJECT SCOPE : The Project includes the engineering / detail design, material procurement, fabrication, testing, transportation, construction /installation, pre-commissioning / mechanical completion, assistance for commissioning, start up and performance testing / acceptance of the FACILITIES  Approximately 11 MMSCFD of Lean Gas, 29 MMSCFD of Sour Gas and 4600 BPD of Condensate will be supplied from the upstream Facilities to the KGOC Gas and Condensate Export System Project  The FACILITIES shall comprise the following:  2 trains of export gas compressors,2 condensate pump sets,scraper launcher at Al Khafji(Saudi Arabia)  110 Km, single 12”NB Multi-phase pipeline that shall be installed approximately 4 Km in onshore Saudi Arabia, 47 Km offshore and 59 Km in onshore Kuwait  Tie-in Facility including scraper receiver at Intermediate Slug Catcher (ISC) at KOC in Kuwait  A Fibre Optic Cable (FOC) for leak detection and communication purposes to be laid along the entire pipeline length Client- Kuwait Gulf Oil Company (KGOC) Responsibilities: Worked Partially with following responsibilities.  Coordination with subcontractors related to project schedules and monitoring the work progress.  Updating progress measurement and monitoring.  Coordinating with the company and regular submission of weekly/monthly progress reports.  Finalization of Progress curves and updating by weekly basis. Project Title : DETAIL ENGINEERING FOR HOOK-UP OF WELLS AND WELL FLUID PIPELINE TIE-INS OUTLINE OF PROJECT SCOPE : Install topside facilities for the new producers and injectors to be drilled from WHPTs PC‐20 and PC‐80, provide facilities required to hook‐up new well fluid pipelines to meet the processing requirements for new producers and injectors. Additionally, topside modification of PC-63, PC-69, PW-32 and PW-38 platforms related to Hook up of new pig launcher/receiver to Production system are also required to be carried out under current project. Client- ZAKUM DEVELOPMENT COMPANY (ZADCO) Responsibilities: Worked Partially with following responsibilities.  Updating progress measurement and monitoring.  Coordinating with the company and regular submission of weekly/monthly progress reports.  Finalization of Progress curves and updating by weekly basis.
  • 9. Page 9 of 16 Nakibul HAQUE Project Planning & Controls - ECP Project Title : AL DABB’IYA ASR GAS DEVELOPMENT PROJECT- FEED & PROCUREMENT SERVICES OUTLINE OF PROJECT SCOPE : The Al Dabb’iya ASR Gas Development Project plans to extend a number of existing NEB Phase I/II and planned NEB Phase III clusters with new gas wells both onshore and offshore. In addition, a new offshore island dedicated to the ASR project will be constructed. A new gas and condensate processing facility will be provided near to the existing NEB Phase I/II and planned Phase III CPPs; this is referred to as the Al Dabb’iya Gas Plant (DGP). Export routes for gas with spiked condensate and disposal water shall be provided along with the necessary third party utilities to support production. Client- Abu Dhabi Company for Onshore Petroleum Operations Ltd. (ADCO) Responsibilities: Worked Partially with following responsibilities. 1-Maintenance and Control of Janus software for timely and correctly production of required reports. 2-Internal meeting and Co-ordinationwith Projectteam (Engineering,Procurement& quality etc.) 3-Producing weekly, Monthly and other reports. 4-Interaction & Coordination with leads for Timely Proper progress and reporting inputs. Project Title : Jarn Yaphour Field development- FEED & PROCUREMENT SERVICES OUTLINE OF PROJECT SCOPE : Jarn Yaphour is an Oil & Gas field located around 50 Km from Rumaitha field. Process facilitiesfor JY were put on productionfrom 1993 to 1999. The well fluid from JY wells was sent to a manifold station by means of flow lines. An 18” transfer line would then transport the JY productionto Abu Dhabi refinery (Umm Al Nar Refinery). In 1999, all producing 10 wells, processing facilities were mothballed and shut down and 18” transfer line was removed. A decision has been taken to initiate appropriate measures to accelerate depletion and extract of the remaining reserves from the field before abandonment by undertaking an accelerated depletion development. The plan is to re-commission the Jarn Yaphour upstream facilities as well as any downstream facilities on an accelerated basis without jeopardizing the health and safety of general population in the area. It is proposed to gather the well fluids from new wells by a single cluster, processing facility and transfer the JY production to ASR- DGP. The depletion of JY wells is expected to last 7 years. Client- Abu Dhabi Company for Onshore Petroleum Operations Ltd. (ADCO) Responsibilities: Worked Partially with following responsibilities.  Develops,updates,andmaintainsthe PlanningandScheduling system(methods,procedures,time-schedules,physical progress, dashboards,etc.).
  • 10. Page 10 of 16 Nakibul HAQUE Project Planning & Controls - ECP  Definesthe Projectbreakdownstructures.  Plansso as to ensure the workfrontsandtimelydeliveries.  Plansinorderto mitigate risksandreduce costs.  Gets clientapproval of the ScheduleBaseline.  Gets clientapproval of progressclaimedormilestonesachievedin orderto enable invoicing.  Increasesthe projectteammembers’awarenessof the Project Milestones,maindurations,andcritical paths.  Monitorsand controlsthe projectstatus,to detectanydelay,and proposescorrective actionsinordertomitigate risksandprevent any delaywhenassignedtoa projectas andwhennecessary.  Estimatesthe delaylinkedwithchangesandclaimsandprepares the Extensionof Time analysis,incase of delaydue toClient.  Manages the PlanningandSchedulingteam.  Estimatesthe delaylinkedwithchangesandclaimsandtoprepare the Extensionof Time analysis,incase of delaydue toclient.  Preparesthe Weekly/Monthlyprogressreportsforthe Clientand the Internal Reportingforthe ProjectManager.  Providesfeedbackandlessonslearnedinordertoimprove the PlanningandSchedulingmethodsandprovidesinputtothe statisticsof planningdepartment. Senior Project Control Engineer (Nov. 2008 – Jun 2012) 2008 - 2012 Worley Parsons, Singapore Project Title: Vung Ang I 2x600MW Coal Fired Thermal Power Plant-VIETNAM Responsibilities: Work includes analyse,interpret,implementthe technical and Commercial Contractual requirementrelevantto each discipline works,Budget, Scheduling,Cash flow,costforecasting and costcontrolling. Project Title: Power Soraya Cogen CCP Project-SINGAPORE Responsibilities: To prepare weekly, monthly progress reports,Schedule and Budgetcontrol reports,Liaison and coordination with clientand subcontractor for 2x400MW Co-generation Combined Cycle Plant for an EPC Contractor. Project Planning Generate proposal /tender schedules (including bar charts,S-curves, histograms,deliverables lists). Prepare forward load forecasts for the project(s),including monitoring and reporting manpower utilisation. Monitor schedule risk.
  • 11. Page 11 of 16 Nakibul HAQUE Project Planning & Controls - ECP Prepare initial network of activities in simplified form for projectprogramme and ensure integrity of data. Ensure schedules are progressed objectivelyaccording to project procedures. Maintain critical path diagrams and computer analysis ofprogramme to ensure projecttargetdates are met. Establish and maintain activity level integration between Primavera P3 and projectcontrol database (In Control). Analyse the effect of proposed changes to the projectbaseline and enforce the change control authorization process. Provide weekly status reports to project managers and clients identifying projectschedule status and man-power status. Preparation and update of Project Controls sections ofthe Project Execution Plan (PEP), including WBS, CBS, Risk management, contingencymanagement,progress measurement& reporting,project reports,etc. Interface with the PM and Finance to prepare monthlyinternal reports (PCS, FCS, MPRD). Prepares the MPR and assisting the PM in the development and delivery of written/oral presentations to the Client. Project Control Provide specialistprojectcontrol services for the supportof the project control system Assistthe Business Systems Group in the rolloutof the projectcontrol system including initial configuration and contribution to training activities Liaise with projectteams to ensure the correct utilization of the project control system based on projectspecific requirements and corporate guidelines Review and develop data interfaces for third party projectsystems,as required Prepare and control Inter Entity Work Orders Safety – Responsible for personal safetysafe working practices for the Business Systems Customer Sector Group. Understand and follow OH&S procedures. Quality Assurance – Responsible for working within the provisions and guidelines ofthe Quality Assurance system relevantto the Business Systems Customer Sector Group Undertake projectroles,as required,to include:  Take ownership ofthe cost control function and ensure integrityof the data being processed  Interface with projectpersonnel to develop projectforecasts and analyse projectcosts  Supervise any supporting roles in the projectcost control area  Liaise with clients to clarify costrelated issues and develop timelyand meaningful monthlyinvoices.Ensure paymentof invoices according to EPCM contract terms  Preparation of projectinvoices in conjunction with the Accounts Department  Liaise with Clientfor reporting purposes
  • 12. Page 12 of 16 Nakibul HAQUE Project Planning & Controls - ECP  Preparation of monthlyfinancial reports for the project. Also prepare other financial analysis as required on an adhoc basis  Implementfinancial controls including controlling authorizations of expenditure and cash flow projections.  Preparation of budgets in conjunction with engineering and construction team members  Ensure effective coordination and cooperation between other team members,particularlyin regard to cost, planning (forecasting) and procurementmatters. Cost Control Understand all relevantdocumentation pertaining to the construction phase of the project including scope ofservices,conditions ofcontract, project execution plan,projectschedule etc. Work within standard projectcostengineering procedures. Ensure that these procedures complywith contractual reporting requirements and,ifnot, modifying accordingly. Prepare activity plans to accomplish all work required bythe field procedures and to ensure sufficientman-power availability. Liaise with ClientProjectControl personnel as necessary. Prepare costbudgets from the costestimate,and update them on approval of contract changes and budgettransfers. Disseminate budgetinformation to all operating groups,providing clarification and additional information where necessaryand ascertaining commitmentto budgets as the cost target. Generally instilling costawareness in the projectin the project organisation such that capital costs are con-trolled and changes to work scope are identified and quantified. Obtain from operating groups,the latestinformation pertinentto cost analysis and ensuring its accuracyand completeness. Attending meetings concerning costmatters. Maintain a comprehensive material and construction quantitycontrol and reporting system to include the cur-rent status ofbudget, material take off and forecastquantities with inputfrom the HO as required. Liaise with Construction ProjectPlanning Engineer on analysis ofproject status. Reviewing the impactof costand schedule changes upon each other. Identify and analysing deviations and trends againstthe budgets. Investigating such deviations with the relevant group and advising Construction Manager/ProjectControl Manager of issues requiring corrective action. Establish and maintaining all costrecording documentation,providing comprehensive costanalysis and pre-paring forecasts offinal construction costs. Review overall project status and forecasts with Construction Manager / Project Control Manager each month. Prepare and issue Change Flags and Trend Notices to record changes to scope and changes to forecastrespectively. Assistthe Project CostEngineer with the preparation of the monthly Contract Profit Report(CPR) by providing associated back up. Assistwith preparation ofthe monthly man hour backlog reportby supplying MPP data and associated back-up.
  • 13. Page 13 of 16 Nakibul HAQUE Project Planning & Controls - ECP Ensure reconciliation on a quarterly basis between Field CostReports and Accounting Departmentcostand billing information. Prepare final construction coststatistics and advise on effectiveness of procedures and systems for possible developments on future projects. Other Project Done At WP-Singapore ; 102010-00002043/28990 - Mong Duong 1 Consulting Svcs 102010-00004043/29430 - PUB Sludge Treatmnt&Disposal 102010-00005043/29500 - Tech Audit for Elect Pwr Supply 102010-00006043/29750 - Seraya Cogen CCP Project 102010-00018043/31410 - Reins ofGas PI-Paya Lebar Rd 102010-00019043/31420 - High Pressure Proj Work 102010-00020043/31430 - Senoko Switch Hse 'B' Ext 102010-00025043/31830 - CS for High-pressure P/L PrjWks 102010-00042043/D2120 - High Pressure Proj Work 102010-00043043/D3023 - SPS-230kVSH'B Cable Div. Work 102010-00053043/D7204 - Tuas PS Stage 2 Development 102010-00063CS Submarine Crude Oil Pipeline 102010-00072MPC for Gas Transmission 102010-00098Engg Consult.Servs.-Tuas Power 102010-00135QP-FEED for Power Supply Projects to Halul Island& NFA. 102010-00136QP-Studies for Power Supply 102010-00142Engineering Consultancyservices for Design,Construction and Commissioning ofa Gas Transmission Submarine Pipeline Project 102010-00142-1ConsultancySvs for sub-marine 102010-00151Due Diligence ofCCGTassets 102010-00154Green Gas Due Diligence 102010-00162Training for QP's Elect. Engr 102010-00163ConsultancyServices for Pre-Consultation and Master Plan Committee Submission for New Natural Gas Transmission Pipeline from Tuas Power Station to Senoko Metering Station 102010-00167-1Oyu Tolgoi K250 Infrastru 102010-00168DTL3-QRA 102010-00171Engineering Consultancyand ProjectManagementServices for design,Construction and Commission ofGas Transmission Pipelines and Gas Off take Station in Jurong Island and Tuas South 102010-00175EPC for 2nd Compressor atTuas 102010-00180Davao Coal Fired Power Plant 102010-00196Hydraulic Analysis for Phase I 102010-00198E-WTransmission Cable Tunnel 102010-00202Engineering Consultancyand ProjectManagementservices for Diversion Projects of High Pressure Gas Transmission Pipelines 102010-00204MANJUNGPOWER PLANT
  • 14. Page 14 of 16 Nakibul HAQUE Project Planning & Controls - ECP 102010-00205ConsultancyService for Gas Leak and Fire Study on Power Gas Pipeline. 102010-00207CS for Tuas CCP5 at TP Station 102010-00208SCADASystem Statewide – DES 102010-00211TC-3 For EC & PM SVS-GTP& AF 102010-00213EPC Conformance & Negotiations 102010-00215Engineering Consultancyand ProjectManagementServices for Design,Construction and Commissioning ofGas Transmission Pipelines and Gas Off take Stations. 102010-00221FeasibilityStudy 60 MW 102010-00226Coal Gasification Feasibility 102010-00228Senoko EnergyNew Heavy Store 102010-00231ConsultancySvs. for EPC Dossi 102010-00233to reimburse 50% ofexpenses 102010-00236The assessmentofcompliance ofthe 2X400 MW combined Cycle Power Plantas Two IndependentGeneration Facilities. 102010-00240Engg Supportto Cirebon 660MW. Planning & Scheduling Engineer (Mar. 2008 –Sept. 2008) 2008 Foster Wheeler Asia Pacific Pte Ltd, Singapore Project Title: Singapore LNG Terminal Project-PGAS Singapore) Responsibilities: Preparing monthlyinvoicing & submitting to client,updating the project progress and comparing with the baseline, Prepare the monthlytrends status as a part of the projectinput to the monthlyproject report. Highlighting the changes to the scope/costs changes due to scope change or any other reason and establishing the trend for scope and costcontrol of the project. Project Title: Cooling Water new Cells & Rejuvenation Project, BLNG Brunei Responsibilities: Weekly and monthlyprogress monitoring, Schedule and costcontrol, liaison with BLNGand Subcon & management for smooth flow of projectprogress & overcome bottlenecks. Project Title: Brunei LNG (BLNG) Gas Power Plant, Brunei Responsibilities: Liaison with BLNGmanagement, Project Controls/Planning/Scheduling Engineer for the Power & CWSR Projects Responsible for creating Level-1 to Level-3 schedules Responsible to highlightCritical Path of the Project at a level of presentation,suitable for conveying an understanding ofthe projectscope, targets and goals. Operate progress measurementand reporting systems to identify actual progress versus the plan.
  • 15. Page 15 of 16 Nakibul HAQUE Project Planning & Controls - ECP Responsible for coordinating Engineering,procurementand Construction Phases Responsible for coordinating Design/engineering matters in view of Project requirements and achievements Preparation of various reports including S-Curves & Rundown Charts Responsible to ensure Projectcostis within planned Budget Responsible to review Contractors Level-4 Schedules and mitigate interface Ensure activity weightings are compliant with estimate. Perform status and progress updates,ensuring progress reported is a true reflection of work achieved. Planning & Scheduling Engineer (Jan. 2007 –Feb. 2008) 2007-2008 Olayan Descon Industrial Company, KSA Client/Project Title: Rabigh Refinery & Petrochemical Project, Saudi Arabia Responsibilities: Identify Project cost,Quantities and Man-hours that reflect the agreed scope of Work & Budget for the Provision of Services Pertaining to all Engineering Disciplines. Setting up the proper Departmental ManagementSystem in each departmentand the complete projectas whole,using ISO9000 Total Quality ManagementSystem. Preparing the complete Tasks/works to be done on daily/weekly/monthly basis and thus for entire project. Client/Project Title: Alwaha PDH/PP Project Al-Jubail, Saudi Arabia Responsibilities: Preparation of Labour,Non-Labour and Materials estimates and managing Variance Orders. Preparation of duties functions,responsibilities,reporting documents and authorities for designations for execution of works.Increasing the Quality of works,Productivity, Performance (CPI& SPI). FEDC Cum Planning Engineer (Mar. 2004 –Jul. 2006) 2004-2006 Descon Engineering LLC ,QATAR Client/Project Title: Dolphin Energy Onshore LNG Project, Qatar Responsibilities: Preparation,Submission and Execution of Primavera P3 Schedule.Monthly progress reportpreparation.Execution &Control of Variance Orders. Making Manpower Histograms,S-Curve and forecasting ofMan, Material and Machines Client/Project Title: Qatar Gas LNG Debottlenecking Project, Qatar Responsibilities: Prepare work package for execution of job within project Schedule and Cost for both Expansion and shutdown.Meeting and coordination with Clientand Subcon for smooth control on project. Client/Project Title: Olefin Petrochemical Project, Qatar
  • 16. Page 16 of 16 Nakibul HAQUE Project Planning & Controls - ECP Responsibilities: Documentation and computer back-up data controls,Projectcontrol software such as P3, DPMS installation and monitoring their Implementation.Preparing PEP,Risk assessmentPlan and Progress Reports. Engineer (Mechanical/Piping) (Aug 2003 –Jan. 2004) 2003-2004 SBG-PCM Group LLC, KSA Client/Project Title: Saudi PetrochemicalCompany (SADAF), Saudi Arabia Responsibilities: Performed engineering drawings review,supervision oferection,testing and commissioning activities ofmechanical equipment. Client/Project Title: Jubail United PetrochemicalProject (JUPC), Saudi Arabia Responsibilities: Preparation of tender specification,tender evaluation,detailed review of engineering drawings.Reviewing ProjectExecution Plan & Safety Plan and Lifting Plan. Client/Project Title: Yanbu PetrochemicalCompany Project (YAMPET) Responsibilities: Saudi Arabia- Preparation of As-builtDrawings.Calculation ofBill of Materials with help of Plot plan,ISOs and Sectional Drawings.Site Progress Monitoring and reporting to top Management.