REHABILITATION
OF THE HONORÉ MERCIER BRIDGE
FEDERAL SECTION
WORK PLAN
2014
FOLLOW UP ON THE PROJECT
Pier 14
3
Ramp 4
139 SLABS
INSTALLED
Ramp 2
188 SLABS
INSTALLED
Ramp 3
120 SLABS
INSTALLED
+ 73 FOR THE
BIKE PATH
FEDERAL ...
FEDERAL SECTION
2/3 OF THE WORK COMPLETED BEFORE 2014
SUMMARY OF THE WORK BEFORE 2014
636 SLABS
REPLACED
346 SLABS
TO BE I...
WORK PLANNED IN 2014
6
XX
X
Pier 14
Pier 27
2014 WORK
120 SLABS TO INSTALL
+ 73 SLABS
FOR THE BIKE PATH
X
ONE LANE /
DIRECTION
Work zone
WORK
D...
MALINE ISLAND SECTION
SEAWAY SECTION
CONVERGENCE SECTION
7
2014
8
LASALLElSOUTH-SHOREl
MALINE ISLAND SECTION
TOWARDS THE SOUTH-SHORE
ONE LANE OPEN PER DIRECTION
WORK SCHEDULE
Honoré Mercier Bridge
2014 WORK SCHEDULE
SEVEN CONSECUTIVE WEEKS
APRIL MAY JUNE
JULY AUGUST SEPTEMBER
OVERVIEW OF WORK TO COME
SLABS CUT AND REMOVED
INSTALLATION OF THE NEW CONCRETE DECK SLABS
INSTALLATION OF THE NEW CONCRETE DECK SLABS
NEW VS OLD DECK
NEW
OLD
SLABS ANCHORERD TO STEEL STRUCTURE
HIGH LEVEL OF PRECISION DURING THE INSTALLATION
INSTALLATION OF NEW BEARING DEVICES
INSTALLATION OF NEW EXPANSION JOINTS
POST-TENSIONING OF THE DECK SLABS (INSTALLATION OF
STEEL CABLES)
INSPECTION AND FINAL PAVING OF THE BRIDGE
22
MERCIERBRIDGE.CA
of 22

Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

Half of the Honoré Mercier Bridge will be closed for seven weeks from Friday, June 20, at 9:00 p.m. to Monday, August 11, at 5:00 a.m. One lane will be open per direction while work takes place. During this period, major work will take place day and night to replace a section of the deck on the federal portion of the Honoré Mercier Bridge, as well as to replace expansion joints and bridge bearings, and to carry out paving and marking work.
Published on: Mar 4, 2016
Published in: Engineering      
Source: www.slideshare.net


Transcripts - Mercier Bridge - 2014 JCCBI Work - Presentation of this major Worksite

  • 1. REHABILITATION OF THE HONORÉ MERCIER BRIDGE FEDERAL SECTION WORK PLAN 2014
  • 2. FOLLOW UP ON THE PROJECT
  • 3. Pier 14 3 Ramp 4 139 SLABS INSTALLED Ramp 2 188 SLABS INSTALLED Ramp 3 120 SLABS INSTALLED + 73 FOR THE BIKE PATH FEDERAL SECTION WORK COMPLETED Pier 32 Maline Island East Side Montréal Direction 116 SLABS INSTALLED
  • 4. FEDERAL SECTION 2/3 OF THE WORK COMPLETED BEFORE 2014 SUMMARY OF THE WORK BEFORE 2014 636 SLABS REPLACED 346 SLABS TO BE INSTALLED
  • 5. WORK PLANNED IN 2014
  • 6. 6 XX X Pier 14 Pier 27 2014 WORK 120 SLABS TO INSTALL + 73 SLABS FOR THE BIKE PATH X ONE LANE / DIRECTION Work zone WORK DAY AND NIGHT SEVEN WEEKS SUMMER 2014
  • 7. MALINE ISLAND SECTION SEAWAY SECTION CONVERGENCE SECTION 7 2014
  • 8. 8 LASALLElSOUTH-SHOREl MALINE ISLAND SECTION TOWARDS THE SOUTH-SHORE ONE LANE OPEN PER DIRECTION
  • 9. WORK SCHEDULE
  • 10. Honoré Mercier Bridge 2014 WORK SCHEDULE SEVEN CONSECUTIVE WEEKS APRIL MAY JUNE JULY AUGUST SEPTEMBER
  • 11. OVERVIEW OF WORK TO COME
  • 12. SLABS CUT AND REMOVED
  • 13. INSTALLATION OF THE NEW CONCRETE DECK SLABS
  • 14. INSTALLATION OF THE NEW CONCRETE DECK SLABS
  • 15. NEW VS OLD DECK NEW OLD
  • 16. SLABS ANCHORERD TO STEEL STRUCTURE
  • 17. HIGH LEVEL OF PRECISION DURING THE INSTALLATION
  • 18. INSTALLATION OF NEW BEARING DEVICES
  • 19. INSTALLATION OF NEW EXPANSION JOINTS
  • 20. POST-TENSIONING OF THE DECK SLABS (INSTALLATION OF STEEL CABLES)
  • 21. INSPECTION AND FINAL PAVING OF THE BRIDGE
  • 22. 22 MERCIERBRIDGE.CA